Lots more work in April and May. A new floor was built upstairs. Stud walls were built and electrical cables were installed. As the upstairs windows are very small, the landing window was enlarged to give a means of escape. It was decided to install two more Velux windows in the bedrooms upstairs to give more light.

Stud wall upstairs.

A new chimney will go in here.

Plasterboard being delivered.

Chris fixing some plasterboard.

One of the replacement windows.

One day this will be a bathroom.

Electrical work is started.

Michael enlarges one of the windows.

One of the bedrooms with the plaster boarding well underway.

Michael enlarges one of the windows.